Figure 1. The wooden Akkerwinde bridge, which weighs 360 ton, was lifted more than five metres using Enerpac's digital Synchronous Lift System to position it correctly.
Digital lifting
The new bridge's deck and arches were mounted on an assembly site around 11/2 km away from the bridge's current location over the A7. After assembly, the bridge was lifted to the correct height for its final position, using Enerpac's computer-controlled hydraulic Synchronous Lift System. According to project leader Michel de Jong of Wagenborg Nedlift, "The system works perfectly. We have already used it a number of times, but what was unique about this project was that we had to lift the bottom of the bridge up to 5.10 m, whereas the lift system's highest prop was 4.40 m."
Thanks to its digital and synchronous lifting technology, this Enerpac hydraulic system not only saves a considerable amount of time, but also is highly accurate, meaning the lifting process can be perfectly balanced, monitored, and managed.
Four abutments
The Enerpac Synchronous Lift System is a combination of digital control, switching, and monitoring. Thanks to specific software, lifting (and lowering) is extremely accurate; the lift system can lift even the heaviest loads with a controlled accuracy of 1 mm.
Only four abutments with BLS Stage-Lift double-acting cylinders (one under each corner of the bridge) were needed to lift up the special massive bridge. The BLS cylinders are intended for the "Lift and Crib" system and have integrated supports to make it easier to position underlying padding materials.
The four lift cylinders, with a total capacity of 1000 ton, were placed on hardwood outer cribbing blocks, which were stacked diagonally layer for layer. A new layer of outer cribbing blocks was put down after around each 10 cm of lifting, as seen in Figure 2.